Rothwell Update

Rothwell New Build Update - 07 Sep 14

Following the construction of the main steel frame, the walls are now nearing completion and the main roof section has been installed.

The next phase will see the external ‘Trespa’ cladding installed followed by the main windows and doors making the building water tight before the commencement of the autumn weather