Rastrick Update

Rastrick New Build Update - 15 Jan 15

There is now a great deal of activity on the site, following the Christmas break.

Internally the plastering and painting has begun, floor coverings are been applied to some areas and the building heating system has been partly switched on.

This latest photograph shows the rear of the station.  The concrete pad in the foreground is the base for the training tower, which will be on site by the end of the month.  The rear doors of the engine house, where the fire engines will drive into the station are now fitted