Yorkshire and Humberside Regional Fire Authorities' Regional Management Board

Meeting held on Thursday 27 March at the North Yorkshire Training Centre, Easingwold

Present:

Humberside Fire and Rescue Authority

Councillor D Barkworth (RMB Vice chair)


North Yorkshire Fire and Rescue Authority

Councillor J Fort
Councillor K King


South Yorkshire Fire and Rescue Authority
Councillor J Andrews
Councillor J Bird
Councillor M Cuthbert


West Yorkshire Fire and Rescue Authority
Councillor D Atkinson
Councillor G Beever
Councillor M Coulson (RMB Chair)


Secretariat: Mr M G Barnes
                     Mrs N Houseman


Treasurer : Mr B Wilkinson


In attendance :

Mr C Anderson North Yorkshire
Mr A Trowsdale North Yorkshire
Mr M Smitherman South Yorkshire
Mr J Hoey South Yorkshire
Mr C McIntosh West Yorkshire
Mr M Khuri Humberside
Ms U Harrison Regional Project Support Office


50   Apologies for Absence


Councillor R Light – West Yorkshire Fire and Rescue Authority
Councillor D Engall – Humberside Fire and Rescue Authority


Apologies were also presented on behalf of Mr F Duffield (Chief Fire Officer, Humberside), Mr R Hannigan (Assistant Chief Officer, Humberside),

Mr P Toase (Chief Fire Officer, West Yorkshire), Mr S Pilling (Deputy Chief Fire Officer, West Yorkshire) and Mr N Hutchinson (Chief Fire Officer, North Yorkshire)


51  Chair’s Announcements


Councillors Bird, Atkinson and Beever


It was reported that this would be the final Regional Management Board meeting for Councillor Jane Bird who was to be Lord Mayor of Sheffield in the 2008 / 2009 municipal year and also of Councillors Atkinson and Beever who were due to retire in May 2008.


Members of the Board thanked them for their commitment to, enthusiasm for and support of, the Regional Management Board.


Ursula Harrison – Regional Project Support Office


The Chair wished to thank Ursula Harrison for

the work she had done in respect of the Regional Control Centre and wished her well in her new position within the Government office for East Midlands.


Facilities Management – presentation


This had originally been scheduled to take place  at this meeting but had been postponed at the request of CLG. New dates had been offered for the presentation to take place – these would be

consulted upon by the secretariat.


52  Minutes of the Board at a meeting held on 10 January 2008


In respect of the arrangements for the appointment of a Regional Control Centre Director (Min no. 44 refers), Members were advised that 22 applications had been received of which 6 had been shortlisted. One application had subsequently been withdrawn.


Interviews for the post would be held on 8 May 2008 and the panel would comprise Councillors Andrews (South Yorkshire), Barkworth (Humberside), 

Coulson (West Yorkshire) and Fort (North 

Yorkshire).


Resolved


That the Minutes be signed by the Chair as a correct record.


53  Urgent Items


None.


54  Admission of the Public


There were no items which required the exclusion of the public and press.


55  Declarations of Interest


There were no declarations of interest in any matter under consideration at the meeting


56  Audit Commission Report – Review of Arrangements Supporting the Yorkshire and Humberside RMB


The Secretary submitted a report which advised of the content of the draft report of the Audit Commission, “Review of Arrangements supporting the Yorkshire and Humberside Regional Management Board”.


Members were advised that the report, circulated to the four Chief Fire Officers / Chief Executives of the constituent fire authorities but not to the RMB itself, not only identified how the constituent authorities had met their shared responsibilities but it also went beyond the original remit of the RMB and requirements placed upon it by the national framework document ie. delivery of six strategic functions.


The document contained a number of factual errors and also raised concerns with regard to both contractual capacity and the extent of delegated powers afforded to the RMB, the latter having been the subject of formal resolution by the constituent authorities upon establishment of the RMB.


Members commented upon the findings of the draft report and reaffirmed the original decision for the RMB not to have a dedicated budget and to act according to the six strategic functions only (as expected by Communities and Local Government).


Resolved


(i) That the report be noted;


(ii) That a letter be forwarded by the Chair to the RMB to the Audit Commission inviting a representative to meet with members of the Board prior to finalization of the review; and


(iii) That some research be undertaken in respect of the operation of Regional Management Boards in other regions to identify best practice and to learn how this may be used during an Audit Commission benchmarking exercise.


Strategic Functions – Update


57  Resilience


The Chief Fire Officer (South Yorkshire) submitted a report which updated Members on resilience matters and the New Dimension project. A list had been circulated at the meeting which identified the exercises which had taken place since November 2004 in the region in respect of the resilience
programme.


Members were advised of progress in the following areas;


• Champion Member involvement and resilience management


• Mass decontamination, Hazardous and Unidentified Substance Incidents


• Urban Search and Rescue (USAR) – full complement now received


• One additional prime mover in each constituent authority. Clarification awaited with regard to insurance liabilities


• Command and Control


• Asset Transfer and Long Term Capability Management


• Regional Resilience Issues


• Impact of the recent flooding


• Regional emergency planning – business case to extend role had been accepted by CLG


Resolved


(i)  That the report be noted; and


(ii)  That a letter be forwarded on behalf of the Regional Management Board in response to Sir Ken Knight’s flooding report emphasizing the preference that Fire Service flood response activity should become a statutory duty.


58  Regional Control Rooms


Consideration was given to a report of Chief Fire Officer (West Yorkshire) which updated Members on the status of the Yorkshire and Humberside
FireControl Regional Control Centre project.


Members were advised of the current position with regard to;


• Data capture and migration toolkit – delayed to

mid-May


• Cut-over arrangements – implications for West Yorkshire as first transferring authority


• Finance – implementation funding (£300,000 available for the region with more to follow over

3-year period)


• Business case – anticipated publication June 2008, financial information being collated with regard to baseline and future costs (CLG anticipated £20m reduction in control centre costs nationally)


• Cost apportionment


• Establishment of company – further independent legal advice had been sought – preference would be “limited by guarantee” method (no material 

difference between this and share capital company if all issues were adequately covered in the documents of incorporation). Target date for incorporation – end September 2008. Draft Heads of Agreement had been produced for consideration by the constituent authorities


• RMB to operate as shadow Company Board – possible requirement to meet as the shadow board to agree a number of issues which may be ratified as soon as possible after incorporation


• Requirement to consider precise governance arrangements, appointment of directors etc


• Appointment of Regional Control Centre Director (interviews to be held on 8 May – panel to comprise Cllrs Coulson, Barkworth, Andrews and Fort)


• Firelink


Resolved


(i) That the report be noted;


(ii) That Mr Robin Graham, Humberside FRA, be thanked for his work in producing the draft Heads of Agreement; and


(iii) That consideration be given to the possibility of arranging a meeting of the shadow company board.


59  Common Services


The Assistant Chief Officer / Director of Community Protection (Humberside Fire and Rescue Service) submitted a report which advised of the progress made with the work in the Common Services strategic functional theme and specifically in the following areas;


• Unwanted Fire Signals procedure complete pending confirmation of legal issues concerning licensing arrangements


• Domestic sprinklers – draft protocol prepared for consultation


• Investigations into feasibility of regional enforcement protocol in response to Regulation and Enforcement Bill


• Home Fire Safety Checks – regional framework available for sign off


• Operational collaboration – work ongoing – 

awaiting issue of national guidelines / templates and sub-group reports


Resolved


That the report be noted.


60  Procurement


Consideration was given to a report of the Assistant Chief Officer (South Yorkshire) which provided Members with an update on progress within the
procurement workstream.


It was reported that the evaluation of the telecoms infrastructure as reported to the January meeting of the Board would be the subject of a further report to the July 2008 meeting.


Members were further advised that both Derbyshire and Nottinghamshire had made an approach to join in with a collaborative venture – a scoping meeting had been arranged. In response to a query raised about a requirement to purchase from Firebuy, it was reported that any decision not to do so would need to be supported by a business case to be
submitted to CLG. Members were advised also of the funding dilemma faced by Firebuy in terms of real costs and the shortfall of government grants.


Resolved


(i) That the report be noted;


(ii) That the regional project to procure Personal Protective Equipment across the four authorities be endorsed;


(iii) That the appointment of a consultant to conduct the assessment of the four services’  telecommunications frameworks be noted; and


(iv) That the organization of a Regional Procurement Seminar held on 13 March 2008 be noted; and


(v) That the regular production of a procurement newsletter be noted.


61 Training


The Assistant Chief Fire Officer / Director of Human Resources (North Yorkshire) submitted a report which updated members on the Training function and specifically on the following issues;


• Regional leadership project – feedback awaited prior to development of action plan


• Regional best value-style training review outcomes


• National firefighter selection tests – application form had been revised following earlier feedback – this would be monitored and be the subject of a report to a future meeting


• Project initiation document – revised version


• Phase 1 Firefighter development – work ongoing to produce regional framework


Resolved


(i) That the report be noted;


(ii) That approval be given to the updated draft Project Initiation Document as attached to the report now submitted; and


(iii) That a report be submitted to a future meeting advising of the outcome of the revisions to the Phase 1 Firefighter development framework.


62  Personnel and HR Management


Consideration was given to a report of the Director

of Human Resources (West Yorkshire Fire and  Rescue Service) which advised of progress with
regional collaboration on human resource issues as follows;


• Regional Control Centre – staffing issues to be resolved, and specifically matters related to TUPE


Resolved


(i) That the report be noted;


(ii) That approval be given to the combination of the Human Resources and Training functions for RMB purposes under the leadership of North Yorkshire Fire and Rescue Service; and


(iii) That a letter of thanks and best wishes be forwarded from the Chair on behalf of Members of the Regional Management Board to Allan Hughes

who retired from the West Yorkshire FRS at the end of March 2008 and who had formerly been the lead officer for the Personnel and HR Management function.


63  Programme Management – Update


Consideration was given to a report of the Deputy Chief Fire Officer (North Yorkshire Fire and Rescue Service) which provided a summary of work being conducted within the Region and which advised of the progress made in each strategic functional area on specific projects.


Four areas were showing “amber” (potential overrun / resource difficulties) and no projects were marked as “red” (behind schedule).


Resolved


That the report be noted.


64  Programme of Meetings 2008 / 9


The Secretary to the Board submitted a report which identified dates for the 2008 / 2009 Programme of meetings.


Resolved


That the programme of meetings for 2008 / 2009 be approved as follows;

Thursday 24 July 2008 (AGM)11 a.m.    Humberside

Thursday 2 October 2008  11 a.m.    West Yorkshire

Thursday 8 January 2009  11 a.m.   South Yorkshire
Thursda  26 March 2009   11 a.m.    North Yorkshire

65  Date of Next Meeting


Resolved


(i) That a meeting of the RMB be convened on a mutually convenient date in West Yorkshire to receive the CLG presentation regarding Facilities Management (Min no. 51 refers); and


(ii) That the next meeting of the Yorkshire and Humberside Fire Authorities’ Regional Management Board be held on Thursday, 24 July 2008 at Humberside FRS Headquarters, Hull.


Chair